Juniper Street - Before

Water and Sewer

Juniper Street Stormwater Project

We are updating stormwater pipes and repairing streambanks on Juniper Street. This will reduce flooding. Work also will help stormwater channels handle the flow of water through the system. 

Project Details

 
Type:
Stormwater
Budget:
$221,491
Project Lead:
Stormwater Management
Contractors:
Hazen and Sawyer (Design), White Oak Construction (Construction)

Contact

 

Todd Rall
Project Manager
919-996-4006

Lead Department:
Engineering Services
Service Unit:
Stormwater

Planning

This phase is complete.

Phase Contacts

 

Todd Rall
Project Manager
919-996-4006

Lead Department:
Engineering Services

Design

This phase is complete.

Phase Contacts

 

Todd Rall
Project Manager
919-996-4006

Lead Department:
Engineering Services

Construction

Date Range:
-

Construction is underway. Crews prepared the worksite for construction. They are now working on curb and gutter. 

A section of Juniper Street will be closed during construction (November - February). Residents living on this street will have access to their homes. Please follow this detour:

  • Traffic on the eastside of Juniper Street should take Picardy Drive to Laurel Hills Road
  • Traffic on the westside of Juniper Street should take Spruce Drive to Boxwood Road

Work hours are Monday through Friday 7 a.m. to 6 p.m. There’s no work on the weekend (emergencies or with City approval only).

Phase Contacts

 

Todd Rall
Project Manager
919-996-4006

Lead Department:
Engineering Services

Complete

Phase details coming soon.

Phase Contacts

 

Todd Rall
Project Manager
919-996-4006

Lead Department:
Engineering Services

We are looking at stormwater issues in the right-of-way or areas that are public property. 

Background

We discovered these drainage issues during the Laurel Hills Area Watershed Study. You can request a copy at 919-996-3940 or by email.

After the study, we ranked the project on its severity and need. 

Schedule

Date Activity
Fall 2017 - Spring 2018 Project planning period
Late Fall 2018 Project design complete
Winter 2019 Permitting process complete
Late Fall 2019 Easement acquisition and construction bid complete; Construction underway
Winter 2020 Project construction complete