brockton drive dam

Water and Sewer

Brockton Drive Dam Rehabilitation

Phase 2

We are replacing the structure at the lower dam on Brockton Drive Lake with a roller-compacted concrete structure. The project addresses dam safety concerns, reduces the frequency and severity of flooding, and improves water quality.

The road will be closed between Bayliner Drive and Gentilly Place until the project is complete. 

Project Details

 
Type:
Lakes, Streams, and Dams
Budget:
$4.2 million
Project Lead:
Stormwater Management
Contractors:
CDM Smith, Inc. (Design), Thalle Construction (Construction)

Contact

 

Gilles Bellot, PE
Project Manager
919-996-4001

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Planning

This phase is complete.

Phase Contacts

 

Gilles Bellot, PE
Project Manager
919-996-4001

Lead Department:
Engineering Services

Design

This phase is complete.

Phase Contacts

 

Gilles Bellot, PE
Project Manager
919-996-4001

Lead Department:
Engineering Services

Construction

Construction to the lower dam is underway. We've closed Brockton Drive until construction is complete in early 2021. 

Completed Work

  • Relocated the sewer line in the project area;
  • Installed the re-designed cofferdam. The temporary sheet pile cofferdam will hold off lake water during construction. The re-design added some more time to the construction schedule, but we needed to make adjustments because of field conditions;
  • Added a bypass pipe for the cofferdam; and,
  • Excavated the area for the new dam and concrete structure. 

Ongoing Work

The contractor is now constructing the concrete structure for the dam. This will take a few months. 

Note: If you live near the construction fence - place garbage cans on the left side of the entrance for pickup during construction.  

Detour

The road will be closed to all traffic between Bayliner Drive and Gentilly Place. Detour signs are rerouting traffic around the construction area through Whitehall Avenue, Hoyle Drive, and E. Millbrook Road. 

Hours

Crews will work Monday - Friday from 7:30 a.m. - 5:30 p.m.
There is no work scheduled on the weekend (unless approved by the City of Raleigh).

The Lake

We've drained the lake since the dam is not functioning right. This will limit the amount of water in the lake and reduce impacts during heavy rainstorms. Crews also have: 

  • Added silt fences to prevent sediment from leaving the construction site; and,
  • Cleared trees in the construction area.
Crews building a new dam structure at a lake on Brockton Drive

Crews building a new concrete structure for the dam on Brockton Drive. They also built a temporary cofferdam to separate the worksite and lake. The cofferdam will be in place during construction. 

Phase Contacts

 

Gilles Bellot, PE
Project Manager
919-996-4001

Lead Department:
Engineering Services

Complete

Phase details coming soon.

Phase Contacts

 

Gilles Bellot, PE
Project Manager
919-996-4001

Lead Department:
Engineering Services

Schedule

Date Activity
Fall 2018 Phase 1 construction complete
Spring 2019 Phase 2 design complete
Summer 2019 Phase 2 construction bid and permitting process
Winter 2020 Phase 2 construction begins
Winter 2021 Phase 2 construction complete

History

The spillway for the upper lake at Brockton Drive was in very poor condition. The upper lake also collected debris and flooded nearby homes during heavy rainstorms. The lower lake dam spillway is too small and there is severe erosion at the outlet of the pipe.

Phase One

The project included replacing stormwater drainage and sanitary sewers, and transforming the upper lake to a stream channel. The stream channel flows through the newly constructed stormwater infrastructure into the lower lake. These changes will improve the channel's water quality and reduce flooding to nearby homes. 

Brockton Drive Dam - Rehabilitation Phase 1

Check out the changes that were made at Brockton Drive Lake to reduce flooding and improve water quality.