City Plaza Renovations

The City is renovating City Plaza on Fayetteville Street (between E. Davie Street and E. Lenoir Street). 

Project Details

 
Type:
City Properties and Facilities
Budget:
$3.1 million
Project Lead:
Construction Management
Contractors:
Kimley-Horn (Design); Harrod and Associates (Construction)

Contact

 

Kelly Ham, PE
Project Manager
919-996-5587

Lead Department:
Engineering Services
Service Unit:
Constructing City-owned Buildings

Programmed

This phase is complete. 

Phase Contacts

 

Kelly Ham, PE
Project Manager
919-996-5587

Lead Department:
Engineering Services

Planning

This phase is complete. 

Phase Contacts

 

Kelly Ham, PE
Project Manager
919-996-5587

Lead Department:
Engineering Services

Design

This phase is complete. 

Phase Contacts

 

Kelly Ham, PE
Project Manager
919-996-5587

Lead Department:
Engineering Services

Construction

Construction is underway. Over the last few months, crews: 

  • Removed plants and soil from the landscape planters in the plaza;
  • Removed the inside of the fountain and pipes beneath it; and, 
  • Ordered new pavers for the plaza. 

Fountain Removal

Crews started removing the fountain the week of March 16. This demolition work should take about two weeks to finish (depending on weather). Road, lane, and sidewalk closures are not expected for this phase. Mainly the area surrounding the fountain and planters is expected to be blocked off. Weekend work may vary.

Planter Repairs 

Repairs to the planters on both sides of the plaza will be ongoing for the next few months. 

Pavers Installation

We're expecting to re-install the pavers at the planters/fountain beginning in April. Then, the rest of the pavers installation in the plaza is expected to continue through the summer/early fall. 

Visiting the Plaza

Visitors have access to buildings in the plaza. There may be temporary sidewalk, lane, or road closures on Fayetteville St. between E. Davie St. and E. Lenoir St. throughout the project. More details coming soon. 

We’ve also adjusted all plaza events going on during construction.

Questions? Email us

Phase Contacts

 

Kelly Ham, PE
Project Manager
919-996-5587

Lead Department:
Engineering Services

Complete

Phase details coming soon. 

Phase Contacts

 

Kelly Ham, PE
Project Manager
919-996-5587

Lead Department:
Engineering Services

The fountain in City Plaza before it's removed to make the public space more open and functional. 

Planters in City Plaza that are being repaired and that will be getting new plants and soil. 

A plan for the renovations in City Plaza. 

Schedule

Date Activity
January 2018 Project design began
Spring 2019 Project design complete
Fall 2019 Project construction begins
Summer/Fall 2020 Project construction complete