City Plaza Renovations

Maintaining City Properties

We are renovating City Plaza on Fayetteville Street (between E. Davie Street and E. Lenoir Street). This project will improve the function and accessibility of the plaza.

The road at City Plaza reopened Nov. 23.

Project Details

 
Type:
City Properties and Facilities
Budget:
$3.1 million
Project Lead:
Construction Management
Contractors:
Kimley-Horn (Design); Harrod and Associates (Construction)

Contact

 

Kelly Ham, PE
Project Manager
919-996-5587

Lead Department:
Engineering Services
Service Unit:
Constructing City-owned Buildings

Programmed

This phase is complete. 

Phase Contacts

 

Kelly Ham, PE
Project Manager
919-996-5587

Lead Department:
Engineering Services

Planning

This phase is complete. 

Phase Contacts

 

Kelly Ham, PE
Project Manager
919-996-5587

Lead Department:
Engineering Services

Design

This phase is complete. 

Phase Contacts

 

Kelly Ham, PE
Project Manager
919-996-5587

Lead Department:
Engineering Services

Construction

Completed Work

  • Removed plants and soil from the landscape planters in the plaza;
  • Removed the fountain in the plaza;
  • Installed pavers in the plaza; and, 
  • Installed expansion joints for buildings in the plaza. 

Final Items

The contractor is almost finished with landscaping in the planters and final items in the plaza. We are on track to finish the work this week. 

Fayetteville Street at City Plaza reopened Monday, Nov. 23.

Phase Contacts

 

Kelly Ham, PE
Project Manager
919-996-5587

Lead Department:
Engineering Services

Complete

Phase details coming soon. 

Phase Contacts

 

Kelly Ham, PE
Project Manager
919-996-5587

Lead Department:
Engineering Services

The fountain in City Plaza before it's removed to make the public space more open and functional. 

Planters in City Plaza that are being repaired and that will be getting new plants and soil. 

A plan for the renovations in City Plaza. 

Schedule

Date Activity
January 2018 Project design began
Spring 2019 Project design complete
Fall 2019 Project construction begins
Fall 2020 Project construction complete