A crack in pavement from a failing stormwater pipe that's close to the entrance of a storage facility

Water and Sewer

Chapel Hill Road Drainage Improvements

Drainage Assistance Program

There is a failing stormwater pipe that goes through the Raleigh-Cary Self Storage Center. The pipe has caused sinkholes and safety concerns for people using the facility.

Project Details

 
Type:
Stormwater
Budget:
$255,000
Project Lead:
Stormwater Management
Contractors:
WSP (Design)

Contact

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Pre-Approval

This phase is complete. 

Phase Contacts

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services

Planning

This phase is complete. 

Phase Contacts

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services

Design

This phase is complete. 

Phase Contacts

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services

Right of Way Acquisition

We have all required easements for the project. Originally, construction was expected to start in June 2020. But, we rebid the project multiple times due to budget and project constraints. 

We expect construction to start in January 2021 after we complete the most recent bid.

 

 

Phase Contacts

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services

Construction

Phase details coming soon. 

Phase Contacts

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services

Complete

Phase details coming soon. 

Phase Contacts

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services

Schedule

Date Activity
August 2018 Project planning and design phase
April 2019 Project design complete
January 2021 Project construction begins
February 2021 Project construction complete