Area for new Centennial Pkwy sidewalk

Transit, Streets, and Sidewalks

Centennial Parkway Sidewalk Project

We are installing a new sidewalk!

The City will install a sidewalk along the south side of Centennial Parkway from Avent Ferry Road to Nazareth Street.

Project Details

 
Type:
Sidewalks
Budget:
$200,000
Project Lead:
Roadway Design & Construction
Contractors:
Design by City Staff

Contact

 

Cordis Yates-Thompson
Project Manager
919-996-4055

Comment Form

Lead Department:
Engineering Services
Participating Department:
Transportation
Service Unit:
Roadway Design and Construction

Subscribe

 

Design

The design phase is complete. We are scheduled to advertise the project for construction bids later this fall.

Lead Department:
Engineering Services

Construction

Construction Complete 

Lead Department:
Engineering Services

Complete

The project is complete.

Lead Department:
Engineering Services

Schedule

Date Description
Summer 2020 Project to Construction Bid
Early Winter 2021 Start Construction
Summer 2021 Project Complete