Area for new Centennial Pkwy sidewalk

Transit, Streets, and Sidewalks

Centennial Parkway Sidewalk Project

We are installing a new sidewalk!

The City will install a sidewalk along the south side of Centennial Parkway from Avent Ferry Road to Nazareth Street.

Project Details

 
Type:
Sidewalks
Budget:
$200,000
Project Lead:
Roadway Design & Construction
Contractors:
Design by City Staff

Contact

 

Cordis Yates-Thompson
Project Manager
919-996-4055

Comment Form

Lead Department:
Engineering Services
Participating Department:
Transportation
Service Unit:
Roadway Design and Construction

Subscribe

 

Design

The design phase is complete. We are scheduled to advertise the project for construction bids later this fall.

Lead Department:
Engineering Services

Construction

Updated May 12

The contractor is installing the sidewalk along the south side of the roadway. There may be some lane closures as the work on this project progresses. We thank you for your patience and understanding as crews complete the new sidewalk. 

Next Steps

 

Complete Project

Lead Department:
Engineering Services

Schedule

Date Description
Summer 2020 Project to Construction Bid
Early Winter 2021 Start Construction
Late Spring 2021 Project Complete