We are installing a new sidewalk!

The City will install a sidewalk along the south side of Centennial Parkway from Avent Ferry Road to Nazareth Street.

Project Details

 
Type:
Sidewalks
Budget:
$200,000
Project Lead:
Roadway Design & Construction
Contractors:
Design by City Staff

Contact

 

Cordis Yates-Thompson
Project Manager
919-996-4055

Comment Form

Lead Department:
Engineering Services
Participating Department:
Transportation
Service Unit:
Roadway Design and Construction

Subscribe

 

Design

The design phase is complete. We are scheduled to advertise the project for construction bids later this fall.

Lead Department:
Engineering Services

Construction

Updated Summer 2021

The contractor is installing the sidewalk along the south side of the roadway. There may be some lane closures as the work on this project progresses. We thank you for your patience and understanding as crews complete the new sidewalk. 

Most of the new sidewalk is installed. The contractor is waiting on a private utility company to relocate their lines before they can finish the project.

Next Steps

 

Complete Project

Lead Department:
Engineering Services

Schedule

Date Description
Summer 2020 Project to Construction Bid
Early Winter 2021 Start Construction
Summer 2021 Project Complete