Area for new Centennial Pkwy sidewalk

Transit, Streets, and Sidewalks

Centennial Parkway Sidewalk Project

We are installing a new sidewalk!

The City will install a sidewalk along the south side of Centennial Parkway from Avent Ferry Road to Nazareth Street.

Project Details

 
Type:
Sidewalks
Budget:
$200,000
Project Lead:
Roadway Design & Construction
Contractors:
Design by City Staff

Contact

 

Cordis Yates-Thompson
Project Manager
919-996-4055

Lead Department:
Engineering Services
Participating Department:
Transportation
Service Unit:
Roadway Design and Construction

Subscribe

 

Design

The design phase is complete. We are scheduled to advertise the project for construction bids later this fall.

Lead Department:
Engineering Services

Construction

Updated June 2020

Construction contracts are routing. This project has been combined with the Raleigh Boulevard Sidewalk Project and the Old Deer Trail Sidewalk Project for the construction phase.

Next Steps

 

Construction is scheduled to begin this summer.

Lead Department:
Engineering Services

Schedule

Date Description
Spring 2020 Project to Construction Bid
Summer 2020 Start Construction
Winter 2021 Project Complete

Related Projects