Bragg Street Culvert Replacement

Stormwater System Upgrade

We are replacing a culvert at the intersection of Bragg Street and S. State Street. The pipe carries water through the stormwater system when it rains. It is failing for two reasons:

  • Age; and,
  • A drinking water line is interfering with the culvert affecting stormwater flows.

Project Details

 
Type:
Stormwater
Budget:
$706,439
Project Lead:
Stormwater Management
Contractors:
CDM Smith (Design); Carolina Civilworks (Construction)

Contact

 

Todd Rall
Project Manager
919-996-4006

Lead Department:
Engineering Services
Participating Department:
Water
Service Unit:
Stormwater

Subscribe

 

Planning

This phase is complete. 

Phase Contacts

 

Todd Rall
Project Manager
919-996-4006

Lead Department:
Engineering Services

Design

The design for this project is complete. We will be upgrading the system to make it easier and safer for water to flow through the city when it rains. We will be: 

  • Installing a new culvert at the intersection of Bragg Street and S. State Street. Instead of two dual 48" x 36" pipes, there will be one larger 4.5 ft. by 10 ft. culvert on the road. 
  • Realigning the 48" pipe that carries water from S. State Street. 

We got all the required permits for construction. We're also finalizing the construction schedule. Work should begin at the end of March when the culvert is delivered. 

The intersection of Bragg Street and S. State Street facing west.

We will updating the stormwater system at the intersection of Bragg Street and S. State Street heading west toward Spaulding Street. 

Phase Contacts

 

Todd Rall
Project Manager
919-996-4006

Lead Department:
Engineering Services

Construction

Phase details coming soon. 

Phase Contacts

 

Todd Rall
Project Manager
919-996-4006

Lead Department:
Engineering Services

Complete

Phase details coming soon. 

Phase Contacts

 

Todd Rall
Project Manager
919-996-4006

Lead Department:
Engineering Services

Schedule

Date Activity
Winter 2020 Project design started
Winter 2021 Project design complete
Winter/Spring 2021 Project construction begins
Summer 2021 Project construction complete