Bloodworth Street Outfall

The project will replace an existing sewer outfall* and associated sewer lines with approximately 1,900 linear feet of 16 and 24-inch sewer line in the Bloodworth Street area. The outfall runs from its downstream connection just north of Martin Luther King Jr. Blvd. north to the intersection of Bloodworth St. and E. South St.

* Outfall: The point, location, or structure where wastewater discharges from a sewer, drain, or other conduit.

Project Details

 
Type:
Water and Sewer
Budget:
$2,000,000
Project Lead:
Janeen Goodwin

Contact

 

Janeen Goodwin, PE
Senior Project Administrator
Email
Phone:919-996-3494 (Office)
Office Location: 1 Exchange Plaza #620
Raleigh, NC 27601

Lead Department:
Water

Planning

This phase is complete. 

Lead Department:
Water

Design

This phase is complete.

Lead Department:
Water

Construction

Project scheduled to begin construction in Summer 2020.

Lead Department:
Water

Complete

Project scheduled to be completed in Summer 2021.

Lead Department:
Water

History

This replacement project was initially identified as part of the 2014 Sanitary Sewer Capacity Study due to wet weather capacity shortfalls. The Study stated that limited capacity causes the model to predict future overloads and overflows. The risk of overloads and overflows means the project is deemed critical due to potential impact on health and safety.

This replacement project will limit sanitary sewer overflows associated with wet weather events. Surrounding streams and environments are then protected through this limitation. 

Schedule

Date Activity
Summer 2019 Project Design Complete
Ongoing Permitting Complete
n/a Easement Acquisition Complete
Summer 2020 Project Bid Complete
Fall 2020 Project Construction Begins
Fall 2021 Project Construction Complete : Please note construction schedules are subject to change due to unforeseen conditions such as, weather, and construction delays or conflicts.