2015 Water / Sewer Replacement Project #3

Phase 1: Replacement project to prepare sewer system for future demands.

This project will replace 12,700 linear feet of 6 - 8 inch water main line along with main line accessories. In addition, 6,300 linear feet of 6 - 8 inch gravity sewer main line along with main line accessories will be replaced during the life of the project.

The existing water and sewer infrastructure within the project area are aging and in need of replacement.

Project Details

 
Type:
Water and Sewer
Budget:
$4,200,000
Project Lead:
Todd Toler
Contractors:
Park Construction

Contact

 

Todd Toler
Senior Engineer
Phone: 919-996-3476 
Office Location: 1 Exchange Plaza Suite 620
Raleigh, NC 27601

Lead Department:
Water

Planning

This phase is complete.

Lead Department:
Water

Design

This phase is complete.

Lead Department:
Water

Construction

Update on completed and ongoing work:
Euston Drive – Complete and paved.
Milbank Street – Complete and paved.
North King Charles Road – Water and/or sewer mains are installed.  Water service lines replacement started September 2020. 
Holburn Place – Water and/or sewer main is installed. Water service lines to be installed.
Blacklan Circle - Water and/or sewer main is installed.  Water service lines to be installed.
Plymouth Courtt – Water and/or sewer main is installed.
Upon completion of water services on North King Charles Road, Holburn Place, Blacklan Street and Plymouth Court, these streets will be paved.

Park Construction Inc. is 70% complete with construction and continues to proceed with project related work.

Lead Department:
Water

Complete

Phase details will be added when available. 

Lead Department:
Water

History

The project was advertised for bid on Tuesday, April 3, 2019.
A pre-bid meeting was held on Tuesday, May 7, 2019.
Construction bids will be received until 2 pm on Thursday, May 30,2019.

 

 

Schedule

Date Activity
Spring 2020 Project Design Complete
Winter 2021 Permitting Complete
Fall 2020 Easement Acquisition Complete
Winter 2021 Project Bid Complete
Spring 2021 Project Construction Begins
Fall 2022 Project Construction Complete