2014 Sewer Line Replacement

Rehabilitation No. 4

Construction began May 1, 2020 on Ligon Middle School property. The contractor will move to the East South St. area at the end of June, 2020.

The Raleigh Water Capital Improvement Program Asset Management group identified aging and failing sewer infrastructure needing replacement or rehabilitation. Four different areas were identified: Tipton St. across Ligon Middle School grounds and across Martin Luther King Blvd. to Spaulding Street; East Jones Street from North Swain Street to Selwyn Alley; Bragg Street and Spaulding Street area; and the East South Street area.

Project Details

 
Type:
Water and Sewer
Budget:
$1,641,748
Project Lead:
Raleigh Water
Contractors:
Carolina Civilworks

Contact

 

Dennis Lassiter, PE
Senior Project Administrator
Phone: 919-996-3477 
Office Location:1 Exchange Plaza Suite 620
Raleigh, NC 27601

Lead Department:
Water

Planning

Project details to be updated when available.

Lead Department:
Water

Design

Project details to be updated when available.

Lead Department:
Water

Right of Way Acquisition

Project details to be updated when available.

Lead Department:
Water

Construction

Construction began May 1, 2020 on Ligon Middle School property. The contractor will move to the East South St. area at the end of June, 2020.

Lead Department:
Water

Complete

Project details to be updated when available.

Lead Department:
Water

Schedule

Date Activity
n/a Project Design Complete
n/a Permitting Complete
n/a Easement Acquisition Complete
Fall 2019 Project Bid Complete
Summer 2020 Project Construction Begins
Summer 2021 Project Construction Complete

History

The Raleigh Water Capital Improvement Program Asset Management group identifies aging and failing infrastructure all over the City and the Merger Towns. This project was identified in 2014 and assigned a project manager to develop into a design and construction project.