Transit, Streets, and Sidewalks

Peace Street West Streetscape

The Peace Street West project will consist of streetscape improvements between Saint Mary's Street and West Street. 

The project will include:

  • New brick paver sidewalks along both sides of the corridor;
  • Street trees with grates;
  • Pedestrian ramp upgrades; 
  • Traffic signal upgrades with mast arms; 
  • Driveway consolidation;
  • Undergrounding of some overhead utility lines along the corridor; and,
  • Water and sanitary sewer repair work from Bellwood Drive to West Johnson Street.

Project Details

 
Type:
Streets
Budget:
$2.2 Million
Project Lead:
Roadway Design & Construction
Contractors:
Design Consultant - Cole, Jenest, & Stone

Contact

 

Amy Billings, PE
Project Manager
919-996-4103

Comment Form

Lead Department:
Engineering Services
Service Unit:
Roadway Design and Construction

Design

Updated Nov. 14

We are still evaluating construction bids. No bids have been accepted to date.

Lead Department:
Engineering Services

Construction

Phase details coming soon.

Lead Department:
Engineering Services

Complete

Phase details coming soon.

Lead Department:
Engineering Services

History

Peace Street west was previously placed on hold to wait for funding to cover right of way acquisition and construction. The project was recently included in the 2013-2014 Capital Improvement Program, completing the remaining funding necessary to proceed with the project. 

Schedule

Date Activity
February 5, 2015 Public Design Meeting
Spring 2017 City Council Presentation
March 2019 Right of Way and Easement Acquisition
July 2019 Advertise Construction Contract
Winter 2020 Award Construction Contract
Fall 2021 Complete Construction