completed roadway project image of New Hope Church Road

Transit, Streets, and Sidewalks

New Hope Church Road Improvement Project

Improving mobility and connectivity for pedestrian, bicycle, and vehicular traffic

The improvements will include new pavement and restriping between Green Road and Ingram Drive and will widen the roadway from Ingram Drive to Deana Lane. The enhancements will include:

  • A three-lane, curb-and-gutter section;
  • Bike lanes;
  • Sidewalk on both sides of the street;
  • Landscaping and Street Trees;
  • Stormwater and erosion control; and,
  • Culvert replacement. 

The Green Road Sidewalk Project and the New Hope Church Road Project have been combined for construction. The Green Road sidewalk Project completes gaps in the sidewalk along both sides of the road from New Hope Church Rd to Spring Forest Rd.

Project Details

 
Type:
Streets
Budget:
$4.6 million
Project Lead:
Roadway Design & Construction
Contractors:
Ramey Kemp & Associates

Contact

 

Sean Driskill, PE
Project Manager
919-996-4106

Comment Form

Lead Department:
Engineering Services
Participating Department:
Transportation
Service Unit:
Roadway Design and Construction

Subscribe

 

Design

This phase is complete.

Lead Department:
Engineering Services

Construction

Updated Dec. 9

New Hope Church Road project is complete!

The roadway was reopened to traffic in early November.

 

Lead Department:
Engineering Services

Complete

New Hope Church Road project is complete!

A project walk through was held in early November and a punch list was submitted to the contractor. All punch list items are complete and the project is now in the warranty period.

New Hope Church and Green Road Completed - Roadway Design and Construction

Lead Department:
Engineering Services

History

The New Hope Church Road Widening Project was prioritized in the Capital Improvement Program as a major street project.   

Schedule

Winter = January - March, Spring = April - June, Summer = July - September, Fall = October - December
Date Activity
November 29, 2016 Preliminary Plans Public Meeting (25% plan)
November 29, 2017 Design Plan Public Meeting (65% Plan)
April 2019 Complete Right of Way and Easement Acquisition
June 2019 Advertise for Construction Contract
Sept.17, 2019 Award Construction Contract
Jan. 28 2020 Pre-Construction Meeting
Late Feb. 2020 Construction Starts
Spring 2020 through October 24 New Hope Church Road Through Traffic Closure
Winter 2021 Project Complete