New sidewalk is coming to Fox Road!

We are installing missing sections of curb, gutter, and sidewalks along the east and west sides of the street between Spring Forest Road and Balance Fox Drive.

Improvements Include:

  • Curb and Gutter;
  • Sidewalks;
  • Paving;
  • Two bioretention areas; and,
  • Bicycle Lanes on both sides of the street.

 

Project Details

 
Type:
Sidewalks
Project Lead:
Roadway Design & Construction
Contractors:
ST Wooten

Contact

 

Cordis Thompson
Project Manager
919-996-4055

Comment Form

Lead Department:
Engineering Services
Service Unit:
Roadway Design and Construction

Subscribe

 

Design

This phase is complete.

Phase Contacts

 

Cordis Thompson
Project Manager
919-996-4055

Lead Department:
Engineering Services

Construction

The project is complete.

Phase Contacts

 

Cordis Thompson
Project Manager
919-996-4055

Lead Department:
Engineering Services

Complete

Updated Sept. 4, 2020

The bioretention ponds are planted and the final paving and pavement markings are complete. The project now enters the warranty period. There is a one-year construction warranty and a two-year landscape and maintenance period.

Lead Department:
Engineering Services

History

The Fox Road Improvement project will install missing sections of curb and gutter and sidewalks on east and west sides between Spring Forest Road and Balance Fox Drive.

Schedule

Date Activity
Late June 2019 Start Construction
Summer 2020 Project Complete