Buck Jones Road Water and Sewer Replacement

Improvement project will replace aging materials to meet future infrastructure capacity demand.

Construction is set to begin on September 9, 2024. Residents will notice the contractor mobilizing to the site as well as the staging of pipe and equipment in preparation for installation the week of September 16, 2024. Pipe and manhole installation is set to begin the week of September 30, 2024. Project is expected to last for 8 months.

Project Details

 
Type:
Water and Sewer
Budget:
$4,000,000
Project Lead:
Raleigh Water
Contractors:
Park Construction of NC

Contact

 

Courtney Licata 
Senior Engineer
Phone: 919-996-3484 (Office)
Office Location: 1 Exchange Plaza Suite 620
Raleigh, NC 27601

Lead Department:
Water

Subscribe

 

Planning

This project phase is complete.

Lead Department:
Water

Design

Project phase complete.

Lead Department:
Water

Right of Way Acquisition

Check back for future phase details.

Lead Department:
Water

Construction

Construction is set to begin on August 15, 2024. Residents will notice the contractor mobilizing to the site as well as the staging of pipe and equipment in preparation for installation. The contractor is Park Construction of NC.

Lead Department:
Water

Complete

Check back for future phase details.

Lead Department:
Water

Schedule

DateActivity
Summer 2023Project Design Complete
Summer 2023Permitting Complete
n/aEasement Acquisition Complete
Spring 2024Project Bid Complete
Summer 2024Project Construction Begins
Winter 2026Project Construction Complete